The partially completed inventory record for the drive shaft subassembly in the table below shows gr 1 answer below »
The partially completed inventory record for the drive shaft subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory.
a. Complete the last three rows of the record for an FOQ of 60 units. (Enter your responses as integers. A response of “0” is equivalent to being not applicable.)
Item: Driveshaft subassembly Lot Size:
FOQequals=60 units
Lead Time: 3 weeks
Week
1
2
3
4
5
6
7
8 Gross
requirements
30
25
20
25
45
45
40
40 Scheduled
receipts
75 Projected on-hand
inventory
15 Planned
receipts
NB: We do not resell papers. Upon ordering, we do an original paper exclusively for you.
Do you need a similar assignment done from scratch? We have qualified writers to help you. We assure you an A+ quality paper that is free from plagiarism. Order now for an Amazing Discount! Use Discount Code "save15" for a 15% Discount!
Request essay helpYou can trust us for this and even for your future projects